The correct answer is: C. It is not possible to calculate the net profit in advance.
A total cost (+) contract is a type of contract in which the contractor is paid for the total cost of the project, plus a fee. This type of contract is generally used in cases where it is difficult to estimate the cost of the project in advance. The fee is intended to cover the contractor’s profit and overhead.
Option A is incorrect because it is not always possible to estimate the cost of a project easily. For example, if the project is complex or if there are a lot of unknowns, it may be difficult to estimate the cost accurately.
Option B is incorrect because the contractor does not necessarily want to earn a certain amount of profit.
132.3s0 89.4 11.4 132.3c6.3 23.7 24.8 41.5 48.3 47.8C117.2 448 288 448 288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z"/> Subscribe on YouTube