The form Work including the props can be removed from beams, only after A. 3 days B. 7 days C. 14 days D. 21 days

3 days
7 days
14 days
21 days

The correct answer is: C. 14 days.

The formwork can be removed from beams after 14 days of concrete pouring. This is because concrete needs 14 days to gain

288 64 288 64S117.2 64 74.6 75.5c-23.5 6.3-42 24.9-48.3 48.6-11.4 42.9-11.4 132.3-11.4 132.3s0 89.4 11.4 132.3c6.3 23.7 24.8 41.5 48.3 47.8C117.2 448 288 448 288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z"/> Subscribe on YouTube
70% of its compressive strength. Removing the formwork before this time can result in the concrete cracking.

Option A is incorrect because 3 days is not enough time for the concrete to gain enough strength. Option B is incorrect because 7 days is not enough time for the concrete to gain enough strength. Option D is incorrect because 21 days is too long to wait to remove the formwork.