work certified
work uncertified
contract cost
value of plant used in the contract
Answer is Wrong!
Answer is Right!
The correct answer is: A. work certified.
The basis for the payment of cash by contractee under contract is work certified. This means that the contractor is paid for the work that has been completed and certified by the owner or the engineer. The work is certified after it has been inspected and found to be in accordance with the contract specifications.
Option B, work uncertified, is incorrect because the contractor is not paid for