Home » mcq » Civil engineering » Construction planning and management » If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then A. expected time of activity A is greater than the expected time of activity B B. expected time of activity B is greater than the expected time of activity A C. expected time of both activities A and B are same D. none of the above
expected time of activity A is greater than the expected time of activity B
expected time of activity B is greater than the expected time of activity A
expected time of both activities A and B are same
none of the above
Answer is Wrong!
Answer is Right!
The correct answer is: B. expected time of activity B is greater than the expected time of activity A.
The expected time of an activity is calculated as follows:
$E(t) = \frac{(t_o + 4t_m + t_p)}{6}$
where $t_o$ is the optimistic time, $t_m$ is the most likely time, and $t_p$ is the pessimistic time.
For activity A, we have:
$E(t_A) = \frac{(4 + 4 \times 6 + 8)}{6} = 6$
For activity B, we have:
$E(t_B) = \frac{(5 + 4 \times 5.5 + 9)}{6} = 6.33$
Therefore, the expected time of activity B is greater
288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z"/>
Subscribe on YouTube
than the expected time of activity A.