Detailed SolutionResponsibility accounting aims at collecting and reporting costing information
Costing
Department-wise
Cost centre-wise
Function-wise
Product-wise
Answer is Wrong!
Answer is Right!
12. Specific price method of valuing material issue is used when . . . . . . . .
materials are purchased for specific job or work order
materials are subject to natural wastage
prices fluctuate
None of these
Answer is Wrong!
Answer is Right!
Detailed SolutionSpecific price method of valuing material issue is used when . . . . . . . .
13. Match the group of List-I with those of List-II and choose the correct answer List-I List-II a. Direct wages 1. Factory expenditure b. Packing 2. Prime cost c. Depreciation 3. Sales cost d. Legal expenses 4. Office expenses
a-1, b-2, c-3, d-4
a-2, b-3, c-1, d-4
a-4, b-3. c-2, d-1
a-2, b-3, c-4, d-1
Answer is Wrong!
Answer is Right!
14. Budgeted sales of X for March are 18000 units. At the end of the production process for X, 10% of production units are scrapped as defective. Opening inventories of X for March are budgeted to be 15000 units and closing inventories will be 11,400 units. All inventories of finished goods must have successfully passed the quality control check. The production budget for X for March, in units is:
12960
14400
15840
16000
Answer is Wrong!
Answer is Right!
15. If sales budget variance is $57000 and flexible budget amount is $97000, then static budget amount will be
$40,000
$154,000
$164,000
$124,000
Answer is Wrong!
Answer is Right!
16. The process of comparing various financial factors of a company over a period of time is known as
Inter-firm comparison
Ratio analysis
Intra-firm comparison
Inter-industry comparison
Answer is Wrong!
Answer is Right!
17. In service costing, fixed charges are also called as . . . . . . . .
standing charges
variable charges
fixed charges
None of these
Answer is Wrong!
Answer is Right!
Detailed SolutionIn service costing, fixed charges are also called as . . . . . . . .
18. If budgeted annual indirect cost is $60000, budgeted annual quantity of cost allocation base is $3600, then budgeted indirect cost rate will be
15.67 per piece
16.67 per piece
14.67 per piece
13.67 per piece
Answer is Wrong!
Answer is Right!
19. For estimation of each cost pool for cost function, attention must be paid to
cost object hierarchy
management hierarchy
price hierarchy
cost hierarchy
Answer is Wrong!
Answer is Right!
Detailed SolutionFor estimation of each cost pool for cost function, attention must be paid to
20. A cost unit is ________.
the cost per machine hour
the cost per labour hour
a unit of production or service in relation to which costs are ascertained
a measure of work output in a standard hour
Answer is Wrong!