4. Match the following. List-I List-II a. Labour cost variance 1. Actual hours paid (Standard rate – Actual rate) b. Labour rate variance 2. Standard cost – Actual cost c. Efficiency variance 3. Idle hours × Standard rate per hour d. Idle time variance 4. Standard rate (Standard hours – Actual hours worked)

[amp_mcq option1=”a-4, b-3, c-2, d-1″ option2=”a-2, b-3, c-4, d-1″ option3=”a-4, b-1, c-2, d-3″ option4=”a-2, b-1, c-4, d-3″ correct=”option1″]

Detailed SolutionMatch the following. List-I List-II a. Labour cost variance 1. Actual hours paid (Standard rate – Actual rate) b. Labour rate variance 2. Standard cost – Actual cost c. Efficiency variance 3. Idle hours × Standard rate per hour d. Idle time variance 4. Standard rate (Standard hours – Actual hours worked)