{"id":8439,"date":"2024-04-15T03:00:40","date_gmt":"2024-04-15T03:00:40","guid":{"rendered":"https:\/\/exam.pscnotes.com\/mcq\/?p=8439"},"modified":"2024-04-15T03:00:40","modified_gmt":"2024-04-15T03:00:40","slug":"pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration","status":"publish","type":"post","link":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/","title":{"rendered":"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow&#8217; originates, is called earliest start time of the activity D. All the above"},"content":{"rendered":"<p>\r\n    <!-- Check if it's an AMP page -->\r\n            <!-- Non-AMP version -->\r\n        <div class=\"mcq-container\" data-quiz-id=\"quizState_6a9b3fa186ff1\">\r\n                                            <div class=\"option\" data-option-key=\"option1\" data-is-correct=\"false\">\r\n                    The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time                <\/div>\r\n                                            <div class=\"option\" data-option-key=\"option2\" data-is-correct=\"false\">\r\n                    The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time                <\/div>\r\n                                            <div class=\"option\" data-option-key=\"option3\" data-is-correct=\"false\">\r\n                    Earliest occurrence time of the event from which the activity arrow&#039; originates, is called earliest start time of the activity                <\/div>\r\n                                            <div class=\"option\" data-option-key=\"option4\" data-is-correct=\"true\">\r\n                    All the above                <\/div>\r\n                            \r\n            <!-- Feedback messages for non-AMP -->\r\n            <div class=\"feedback\" data-feedback=\"wrong\">Answer is Right!<\/div>\r\n            <div class=\"feedback\" data-feedback=\"right\">Answer is Wrong!<\/div>\r\n        <\/div>\r\n\r\n        <script>\r\n        document.addEventListener('DOMContentLoaded', function () {\r\n            var containers = document.querySelectorAll('.mcq-container');\r\n\r\n            containers.forEach(function(container) {\r\n                var options = container.querySelectorAll('.option');\r\n                var feedbackSelect = container.querySelector('[data-feedback=\"select\"]');\r\n                var feedbackWrong = container.querySelector('[data-feedback=\"wrong\"]');\r\n                var feedbackRight = container.querySelector('[data-feedback=\"right\"]');\r\n\r\n                options.forEach(function(option) {\r\n                    option.addEventListener('click', function() {\r\n                        var selectedOption = option.getAttribute('data-option-key');\r\n                        var isCorrect = option.getAttribute('data-is-correct') === 'true';\r\n\r\n                        \/\/ Remove previous selections\r\n                        options.forEach(function(opt) {\r\n                            opt.classList.remove('correct', 'incorrect');\r\n                        });\r\n\r\n                        \/\/ Add the correct\/incorrect class\r\n                        if (isCorrect) {\r\n                            option.classList.add('correct');\r\n                            feedbackRight.hidden = false;\r\n                            feedbackWrong.hidden = true;\r\n                        } else {\r\n                            option.classList.add('incorrect');\r\n                            feedbackRight.hidden = true;\r\n                            feedbackWrong.hidden = false;\r\n                        }\r\n\r\n                        \/\/ Hide select feedback\r\n                        feedbackSelect.hidden = true;\r\n                    });\r\n                });\r\n            });\r\n        });\r\n        <\/script>\r\n    \r\n    <!--more--><\/p>\n<p>The correct answer is D. All of the above.<\/p>\n<p>In critical path method (CPM) network analysis of projects, the earliest start time (EST) of an activity is the earliest time at which the activity can start, given the start times of the activities that must precede it. The latest start time (LST) of an activity is the latest time at which the activity can start without delaying the project. The latest finish time (LFT) of an activity is the latest time at which the activity can finish without delaying the project. The duration of an activity is the amount of time it takes to complete the activity.<\/p>\n<p>The EST of an activity is equal to the earliest finish time of the activity that must precede it, plus the duration of the activity. The LST of an activity is equal to the latest finish time of the project, minus the duration of the activity.<\/p>\n<p>The critical path is <div class=\"telegram-channel-container\">\r\n        <a href=\"https:\/\/t.me\/pscnotes2025\" target=\"_blank\" class=\"telegram-channel-button\">\r\n            <span class=\"telegram-icon\">\r\n                <svg xmlns=\"http:\/\/www.w3.org\/2000\/svg\" viewBox=\"0 0 496 512\">\r\n                    <path fill=\"white\" d=\"M248,8C111,8,0,119,0,256s111,248,248,248s248-111,248-248S385,8,248,8z M362,177L320,367c-3,14-10,18-20,14l-56-41l-27,26 c-3,3-5,5-10,5l4-63L323,196c5-5-1-7-8-3l-98,62l-42-13c-9-3-10-9,2-14l162-63C351,160,365,164,362,177z\"\/>\r\n                <\/svg>\r\n            <\/span>\r\n            Join Our Telegram Channel\r\n        <\/a>\r\n    <\/div> the path through the network that takes the longest time to complete. The critical activities are the activities on the critical path. The critical path and critical activities determine the earliest possible completion time for the project.<\/p>\n<p>If an activity on the critical path is delayed, the entire project will be delayed. If an activity that is not on the critical path is delayed, the project will not be delayed, but the earliest possible completion time for the project may be delayed.<\/p>\n<p>CPM network analysis is a powerful tool for planning and scheduling projects. It can help to <div class=\"youtube-subscribe-container\">\r\n        <a href=\"https:\/\/www.youtube.com\/channel\/UCNHT8lW-JmLC68rjBfZhdkg?sub_confirmation=1\" target=\"_blank\" class=\"youtube-subscribe-button\">\r\n            <span class=\"youtube-icon\">\r\n                <svg xmlns=\"http:\/\/www.w3.org\/2000\/svg\" viewBox=\"0 0 576 512\">\r\n                    <path d=\"M549.7 124.1c-6.3-23.7-24.8-42.3-48.3-48.6C458.8 64 288 64 288 64S117.2 64 74.6 75.5c-23.5 6.3-42 24.9-48.3 48.6-11.4 42.9-11.4 132.3-11.4 132.3s0 89.4 11.4 132.3c6.3 23.7 24.8 41.5 48.3 47.8C117.2 448 288 448 288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z\"\/>\r\n                <\/svg>\r\n            <\/span>\r\n            Subscribe on YouTube\r\n        <\/a>\r\n    <\/div> ensure that projects are completed on time and within budget.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Join Our Telegram Channel Subscribe on YouTube<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[655],"tags":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v22.2 (Yoast SEO v23.3) - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow&#039; originates, is called earliest start time of the activity D. All the above<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow&#039; originates, is called earliest start time of the activity D. All the above\" \/>\n<meta property=\"og:description\" content=\"Join Our Telegram Channel Subscribe on YouTube\" \/>\n<meta property=\"og:url\" content=\"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/\" \/>\n<meta property=\"og:site_name\" content=\"MCQ and Quiz for Exams\" \/>\n<meta property=\"article:published_time\" content=\"2024-04-15T03:00:40+00:00\" \/>\n<meta name=\"author\" content=\"rawan239\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"rawan239\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity D. All the above","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/","og_locale":"en_US","og_type":"article","og_title":"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity D. All the above","og_description":"Join Our Telegram Channel Subscribe on YouTube","og_url":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/","og_site_name":"MCQ and Quiz for Exams","article_published_time":"2024-04-15T03:00:40+00:00","author":"rawan239","twitter_card":"summary_large_image","twitter_misc":{"Written by":"rawan239","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/","url":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/","name":"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity D. All the above","isPartOf":{"@id":"https:\/\/exam.pscnotes.com\/mcq\/#website"},"datePublished":"2024-04-15T03:00:40+00:00","dateModified":"2024-04-15T03:00:40+00:00","author":{"@id":"https:\/\/exam.pscnotes.com\/mcq\/#\/schema\/person\/5807dafeb27d2ec82344d6cbd6c3d209"},"breadcrumb":{"@id":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/exam.pscnotes.com\/mcq\/pick-up-the-correct-statement-from-the-following-with-regards-to-c-p-m-network-analysis-of-projects-a-the-latest-occurrence-time-of-the-node-of-which-the-activity-arrow-terminates-minus-the-duration\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/exam.pscnotes.com\/mcq\/"},{"@type":"ListItem","position":2,"name":"mcq","item":"https:\/\/exam.pscnotes.com\/mcq\/category\/mcq\/"},{"@type":"ListItem","position":3,"name":"Civil engineering","item":"https:\/\/exam.pscnotes.com\/mcq\/category\/mcq\/civil-engineering\/"},{"@type":"ListItem","position":4,"name":"Construction planning and management","item":"https:\/\/exam.pscnotes.com\/mcq\/category\/mcq\/civil-engineering\/construction-planning-and-management\/"},{"@type":"ListItem","position":5,"name":"Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow&#8217; originates, is called earliest start time of the activity D. All the above"}]},{"@type":"WebSite","@id":"https:\/\/exam.pscnotes.com\/mcq\/#website","url":"https:\/\/exam.pscnotes.com\/mcq\/","name":"MCQ and Quiz for Exams","description":"","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/exam.pscnotes.com\/mcq\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/exam.pscnotes.com\/mcq\/#\/schema\/person\/5807dafeb27d2ec82344d6cbd6c3d209","name":"rawan239","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/exam.pscnotes.com\/mcq\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/d97f17072bfa490596c8f78363955d55?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/d97f17072bfa490596c8f78363955d55?s=96&d=mm&r=g","caption":"rawan239"},"sameAs":["https:\/\/exam.pscnotes.com"],"url":"https:\/\/exam.pscnotes.com\/mcq\/author\/rawan239\/"}]}},"amp_enabled":true,"_links":{"self":[{"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/posts\/8439"}],"collection":[{"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/comments?post=8439"}],"version-history":[{"count":0,"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/posts\/8439\/revisions"}],"wp:attachment":[{"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/media?parent=8439"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/categories?post=8439"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/exam.pscnotes.com\/mcq\/wp-json\/wp\/v2\/tags?post=8439"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}