Time and progress chart of a construction, is also known as A. Bar chart B. Gantt chart C. Modified Mile stone chart D. All the above

Bar chart
Gantt chart
Modified Mile stone chart
All the above

The correct answer is: D. All the above.

A bar chart is a chart with rectangular bars with lengths proportional to the values that they represent. Bar charts are used to compare different categories of data.

A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts show the start and finish dates of the various tasks in a project, as well as the dependencies between them.

A modified milestone chart is a type of bar chart that shows the start and finish dates of the major milestones in a project. Milestone charts are used to track the progress of a project and to identify any potential problems.

All three of these charts are used to represent time and progress in a construction project.