The total of all direct expenses is known as . . . . . . . . cost.

prime
works
production
Both A and B

The correct answer is: Both A and B.

Prime cost is the total of direct material cost and direct labor cost. It is the cost of

75.5c-23.5 6.3-42 24.9-48.3 48.6-11.4 42.9-11.4 132.3-11.4 132.3s0 89.4 11.4 132.3c6.3 23.7 24.8 41.5 48.3 47.8C117.2 448 288 448 288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z"/> Subscribe on YouTube
the materials and labor that are directly involved in the production of a product.

Works cost is the total of prime cost and indirect cost. Indirect cost is the cost of production that is not directly involved in the production of a product, such as factory overhead and administrative costs.

Therefore, the total of all direct expenses is known as prime cost and works cost.