The estimate based on a detailed quantity survey and furnishes the most accurate and reliable estimate possible is known as A. Conceptual estimate B. Definitive estimate C. Probabilistic estimate D. None of these

Conceptual estimate
Definitive estimate
Probabilistic estimate
None of these

The correct answer is: B. Definitive estimate

A definitive estimate is the most accurate and reliable estimate possible. It is based on a detailed quantity survey, which is a process of measuring and estimating the quantities of materials and labor required for a project. The definitive estimate is used to set the budget for a project and to track progress and costs during construction.

A conceptual estimate is a rough estimate of the cost of a project. It is based on preliminary information about the project, such as the size and scope of the project. The conceptual estimate is used to determine whether a project is feasible and to develop a more detailed estimate.

A probabilistic estimate is an estimate of the range of possible costs for a project. It is based on a probability distribution that takes into account the uncertainty of the project’s costs. The probabilistic estimate is used to assess the risk of a project and to develop contingency plans.

None of these is the correct answer.