The correct answer is C. Float.
Float is the amount of time that a task can be delayed without delaying the project’s finish date. It is calculated by subtracting the task’s duration from the amount of time available to complete the task.
Event is a point in time at which something happens. It is represented by a node in a project network diagram.
Duration is the length of time required to complete a task. It is calculated by adding up the durations of all the activities that make up the task.
Constraint is a restriction that limits the options available to the project team. It can be imposed by the project’s scope, schedule, budget, or resources.