Preliminary project report for a road project must contain A. The detailed estimated cost based on detailed design B. The several alternatives of the project that have been considered C. The soil survey, traffic survey, concept design and approximate cost D. The contract documents for inviting tenders

The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders

The correct answer is C. The soil survey, traffic survey, concept design and approximate cost.

A preliminary project report is a document that is prepared to assess the feasibility of a proposed project. It includes a description of the project, its objectives, its scope, its schedule, its budget, and its risks. The report also includes a discussion of the alternatives that have been considered and the reasons for selecting the preferred alternative.

The soil survey is a study of the soil conditions in the area where the project will be built. The traffic survey is a study of the traffic patterns in the area where the project will be built. The concept design is a preliminary sketch of the project. The approximate cost is an estimate of the cost of the project.

The contract documents for inviting tenders are not included in a preliminary project report. These documents are prepared after the project has been approved and are used to invite bids from contractors.

Here is a brief explanation of each option:

  • A. The detailed estimated cost based on detailed design. This is not included in a preliminary project report because the detailed design has not yet been completed.
  • B. The several alternatives of the project that have been considered. This is included in a preliminary project report because it is important to consider all of the alternatives before selecting the preferred alternative.
  • C. The soil survey, traffic survey, concept design and approximate cost. This is included in a preliminary project report because it is important to have this information before making a decision about whether or not to proceed with the project.
  • D. The contract documents for inviting tenders. This is not included in a preliminary project report because the contract documents are prepared after the project has been approved and are used to invite bids from contractors.