Pick up the correct statement from the following with regards to C.P.M. network analysis of projects A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time C. Earliest occurrence time of the event from which the activity arrow’ originates, is called earliest start time of the activity D. All the above

The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above

The correct answer is D. All of the above.

In critical path method (CPM) network analysis of projects, the earliest start time (EST) of an activity is the earliest time at which the activity can start, given the start times of the activities that must precede it. The latest start time (LST) of an activity is the latest time at which the activity can start without delaying the project. The latest finish time (LFT) of an activity is the latest time at which the activity can finish without delaying the project. The duration of an activity is the amount of time it takes to complete the activity.

The EST of an activity is equal to the earliest finish time of the activity that must precede it, plus the duration of the activity. The LST of an activity is equal to the latest finish time of the project, minus the duration of the activity.

The critical path is the path through the network that takes the longest time to complete. The critical activities are the activities on the critical path. The critical path and critical activities determine the earliest possible completion time for the project.

If an activity on the critical path is delayed, the entire project will be delayed. If an activity that is not on the critical path is delayed, the project will not be delayed, but the earliest possible completion time for the project may be delayed.

CPM network analysis is a powerful tool for planning and scheduling projects. It can help to ensure that projects are completed on time and within budget.