PERT analysis is based on A. Optimistic time B. Pessimistic time C. Most likely time D. All the above

Optimistic time
Pessimistic time
Most likely time
All the above

The correct answer is D. All the above.

PERT analysis is a method for estimating the time it will take to complete a project. It is based on three time estimates: optimistic time, pessimistic time, and most likely time. The optimistic time is the shortest possible time that a task could take to complete. The pessimistic time is the longest possible time that a task could take to complete. The most likely time is the time that is most likely for a task to take to complete.

PERT analysis uses these three time estimates to calculate a weighted average time estimate for each task. This weighted average time estimate is then used to calculate the total time it will take to complete the project.

PERT analysis is a valuable tool for project managers because it allows them to estimate the time it will take to complete a project with a high degree of accuracy. This information can be used to develop realistic project schedules and budgets.

Here is a brief explanation of each option:

  • Optimistic time: The shortest possible time that a task could take to complete.
  • Pessimistic time: The longest possible time that a task could take to complete.
  • Most likely time: The time that is most likely for a task to take to complete.
Exit mobile version