Match List I with List II and select the correct answer using the code given below the Lists :
List I (Ultra mega power project at different stages of development)
List II (State)
| A. Sasan | 1. Gujarat |
| B. Mundra | 2. Madhya Pradesh |
| C. Tilaiya | 3. Andhra Pradesh |
| D. Krishnapatnam | 4. Jharkhand |
Code :
[amp_mcq option1=”2 4 1 3″ option2=”3 4 1 2″ option3=”2 1 4 3″ option4=”3 1 4 2″ correct=”option3″]
This question was previously asked in
UPSC NDA-2 – 2016
A. Sasan UMPP: Located in Singrauli district, Madhya Pradesh (2).
B. Mundra UMPP: Located in Kutch district, Gujarat (1). There are multiple power projects at Mundra, including a UMPP won by Tata Power.
C. Tilaiya UMPP: Was planned in Hazaribagh district, Jharkhand (4). This project faced land acquisition and regulatory issues and was eventually abandoned by Reliance Power in 2015.
D. Krishnapatnam UMPP: Located in Nellore district, Andhra Pradesh (3). This project was awarded to Reliance Power but also faced significant delays and issues.
Based on the intended locations, the mapping is A-2, B-1, C-4, D-3, which corresponds to option C (2 1 4 3).