CG Co manufactures a single product T. Budgeted production output of product T during June is 200 units. Each unit of product T requires 6 labour hours for completion and CG Co anticipates 20 per cent idle time. Labour is paid at a rate of Rs7 per hour. The direct labour cost budget for March is

Rs. 6,720
Rs. 8400
Rs. 10080
Rs. 10500

The correct answer is: C. Rs. 10080

The direct labor cost budget for March is calculated as follows:

  • Budgeted production output of product T during March = 200 units
  • Each unit of product T requires 6 labor hours for completion = 6 hours/unit
  • CG Co anticipates 20 per cent idle time = 20%
  • Labor is paid at a rate of Rs7 per hour = Rs7/hour

Therefore, the direct labor cost

d="M549.7 124.1c-6.3-23.7-24.8-42.3-48.3-48.6C458.8 64 288 64 288 64S117.2 64 74.6 75.5c-23.5 6.3-42 24.9-48.3 48.6-11.4 42.9-11.4 132.3-11.4 132.3s0 89.4 11.4 132.3c6.3 23.7 24.8 41.5 48.3 47.8C117.2 448 288 448 288 448s170.8 0 213.4-11.5c23.5-6.3 42-24.2 48.3-47.8 11.4-42.9 11.4-132.3 11.4-132.3s0-89.4-11.4-132.3zm-317.5 213.5V175.2l142.7 81.2-142.7 81.2z"/> Subscribe on YouTube
budget for March is:

  • Budgeted production output of product T during March x Hours per unit x (1 – Idle time%) x Labor rate per hour = 200 units x 6 hours/unit x (1 – 20%) x Rs7/hour = Rs10080

Option A is incorrect because it does not take into account the idle time. Option B is incorrect because it does not take into account the labor rate. Option D is incorrect because it does not take into account the production output.