A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
Answer is Right!
Answer is Wrong!
The correct answer is C. Both A and R are correct.
An activity is critical if any delay in its start or finish will delay the project completion.