A Milestone chart A. Shows the interdependencies of various jobs B. Depicts the delay of jobs, if any C. Points outgoing ahead of schedule of jobs, if any D. None of these

Shows the interdependencies of various jobs
Depicts the delay of jobs, if any
Points outgoing ahead of schedule of jobs, if any
None of these

The correct answer is: A. Shows the interdependencies of various jobs.

A milestone chart is a type of project management tool that shows the major milestones or goals of a project, as well as the dates by which they are expected to be completed. Milestone charts can be used to track the progress of a project and identify any potential risks or delays.

Milestone charts do not typically show the interdependencies of various jobs. This information is typically shown on a Gantt chart, which is another type of project management tool. A Gantt chart shows the start and finish dates for each task in a project, as well as the dependencies between tasks.

Depicts the delay of jobs, if any: This is not a function of a milestone chart. A milestone chart shows the major milestones or goals of a project, as well as the dates by which they are expected to be completed. It does not show the actual dates on which the milestones were completed, or any delays that may have occurred.

Points outgoing ahead of schedule of jobs, if any: This is also not a function of a milestone chart. A milestone chart shows the major milestones or goals of a project, as well as the dates by which they are expected to be completed. It does not show the actual dates on which the milestones were completed, or any jobs that may have been completed ahead of schedule.