Which of the following scheme(s) is/are included under Bharatmala Pariyojana ?
- 1. Develop the road connectivity to border areas
- 2. Development of coastal roads
- 3. Improvement in the efficiency of National Corridors
Select the correct answer using the code given below :
1 only
3 only
2 and 3 only
1, 2 and 3
Answer is Right!
Answer is Wrong!
This question was previously asked in
UPSC NDA-1 – 2023
1. Development of Economic Corridors (around 9,000 km).
2. Development of Inter Corridors and Feeder Routes (around 6,000 km).
3. National Corridor Efficiency Improvement (around 5,000 km, decongestion of existing corridors).
4. Border Road Development and International Connectivity Roads (around 3,400 km).
5. Coastal Road Development and Port Connectivity Roads (around 2,000 km).
6. Development of Greenfield Expressways (around 800 km).