A is correct but R is not correct
R is correct but A is not correct
Both A and R is correct
Both A and R is incorrect
Answer is Right!
Answer is Wrong!
The correct answer is C. Both A and R are correct.
An activity is critical if any delay in its start or finish will delay the
project completion. The earliest finish time (EFT) of an activity is the earliest time at which the activity can be completed, given the start times of its predecessors. The latest finish time (LFT) of an activity is the latest time at which the activity can be completed without delaying the project completion. An activity is critical if its EFT and LFT are the same.In this case, activity 57 has an EFT and LFT of 10, so it is critical. The reason is also correct, as the EFT and LFT of activity 57 are the same.