a-2, b-3, c-4, d-1
a-2, b-4, c-3, d-1
a-1, b-2, c-3, d-4
a-1, b-3, c-4, d-2
Answer is Right!
Answer is Wrong!
The correct answer is: C. a-1, b-2, c-3, d-4.
Here is a brief explanation of each option:
- Option A: This option is incorrect because it matches the Balh Valley Project with Una district, which is incorrect. The Balh Valley Project is located in Mandi district.
- Option B: This option is incorrect because it matches the Bhabour Sahib Project with Sirmaur district, which is incorrect. The Bhabour Sahib Project is located in Kangra district.
- Option C: This option is correct because it matches the Balh Valley Project with Mandi district, the Bhabour Sahib Project with Kangra district, the Giri Project with Sirmaur district, and the Shahnehar Project with Una district.
- Option D: This option is incorrect because it matches the Shahnehar Project with Mandi district, which is incorrect. The Shahnehar Project is located in Una district.