The correct answer is A. 10 mm.
The net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed 10 mm for a safe pile. This is because a pile that settles more than 10 mm per tonne of test load is likely to be unstable and could fail under load.
Option B is incorrect because 15 mm is too much settlement for a safe pile. Option C is incorrect because 20 mm is too much settlement for a safe pile. Option D is incorrect because 25 mm is too much settlement for a safe pile.