The escalation proposal was submitted to the state finance department by theMumbai Metro Rail Corporation(MMRC), which is implementing the 33.5km rail link betweenCuffe Paradeand Seepz, in February.
It is also learnt that the Japan International Cooperation Agency (JICA), which is funding almost 60% of the total project cost, has not released funds for Metro 3 for the past year.