t least two key public projects in Noida the six-lane underpass at the Sector 71 intersection and the under-construction flyover over the Parthala roundabout are staring at delays.
This is because the work productivity at the project sites has dropped significantly over the past few weeks due to exodus of migrant workers in the wake of the lockdown.
As against an earlier labour force of 150, some 20-25 workers are currently working at the Sector 71 intersection site.